Home » Waste plant loses $140K compo bid

Waste plant loses $140K compo bid

The proponent of a controversial waste-to-energy plant has lost its bid to slug Greater Dandenong Council with more than $140,000 in legal costs and planning fees.

On 16 February, VCAT senior member Jeanette Rickards found it “would not be fair in the circumstances” to make a costs order for Great Southern Waste Technologies.

GSWT had sought $131,527 legal costs against the council after being granted a permit for the plant at 70 Ordish Road, Dandenong South.

In late 2019, the council had approved the permit and then rescinded it. In September, GSWT won an appeal at VCAT – despite the council’s opposition.

GSWT also sought the reimbursement of $11,803 of planning application and daily hearing fees.

Ms Rickards dismissed GSWT’s claim that the council had a weak or untenable case because it rescinded its original decision.

“Although GSWT may not have liked this outcome, it was perfectly within the council’s right to rescind its decision.

“An award of costs is not a punishment.”

GSWT submitted that the council belatedly applied for an adjournment to consider the EPA approval for the plant – handed down a week before the VCAT hearing in July.

But despite being given an extra three weeks, the council didn’t provide additional information, GSWT argued.

‘‘Council’s conscious and deliberate decision to proceed to the hearing without preparing a case visited costs consequences upon GSWT and the Tribunal,” GSWT submitted.

“This was especially evident on the first day of the hearing, which was wholly wasted due to Council’s failed, belated, adjournment application.”

The council argued each side should bear its own legal costs and that its case was not without merit.

Greater Dandenong also launched and then withdrew an appeal against the EPA approval – just days out from a 1 February VCAT hearing.

Councillors were advised that the council was unlikely to win the appeal, and faced a potential legal bill of up to $700,000 including GSWT’s costs.

In an out-of-court settlement, the council agreed to bear some of GSWT’s legal costs, according to GSWT.

Then-spokesperson for GSWT, Bill Keating, said construction was at least 12 months away until the plant’s detailed design was finalised.

A viable, ongoing supply of waste also needed to be secured prior to works, Mr Keating said.

The plant is expected to burn 100,000 tonnes a year of municipal household solid waste, commercial and industrial waste to produce 7.9 MW of electricity to the grid.

 

Digital Editions


More News

  • Waste-to-energy submissions open

    Waste-to-energy submissions open

    Public submissions have opened for the upcoming Victorian Parliamentary inquiry into the state’s push for waste-to-energy plants. South-Eastern Metropolitan MP Rachel Payne, who pushed for the inquiry, says there are…

  • Ambulance response times improve in Casey, state targets still unmet

    Ambulance response times improve in Casey, state targets still unmet

    Purchase this photo from Pic Store: 515650 New insights from Ambulance Victoria (AV) shows minor improvements in response times from first responders and turnaround durations in Casey, with an average…

  • $80,000 for Casey-wide Pest Management Strategy

    $80,000 for Casey-wide Pest Management Strategy

    Purchase this photo from Pic Store: 496313 Casey Council has unanimously endorsed a plan to set aside $80,000 to develop a municipality-wide Pest Animal Management Strategy, as growing rabbit infestations…

  • Clyde North safety breaches lead to $700k fine

    Clyde North safety breaches lead to $700k fine

    Purchase this photo from Pic Store: 166670 Construction works in Clyde North have been in the spotlight after roofing company Proform Roofing (Vic) Pty Ltd was fined $700,000 over multiple…

  • $250m Cranbourne South Hindu temple referral pulled for redesign

    $250m Cranbourne South Hindu temple referral pulled for redesign

    Plans for a proposed $250 million Hindu temple precinct in Cranbourne South’s green wedge have been put on hold after the applicant withdrew its Federal environmental referral, citing a redesign…

  • Powers, premiers and poles

    Powers, premiers and poles

    Purchase this photo from Pic Store: 530014 BLAIR: Gday boys, we are back for another week of Let’s Talk Sport and we have plenty happening, so let’s get into it.…

  • Hampton Park waste plan hits home

    Hampton Park waste plan hits home

    Purchase this photo from Pic Store: 470334 Residents are still seeking answers over an advanced-waste plan that’s extending the life of waste facilities near Hampton Park homes, says Casey Residents…

  • Casey Pushes statewide green streets expansion through MAV

    Casey Pushes statewide green streets expansion through MAV

    As part of the City of Casey’s membership with the Municipal Association of Victoria (MAV), the council will be calling on a Green Streets initiative at the State Council meetings…

  • Women Making It Work marks 20 years with book launch

    Women Making It Work marks 20 years with book launch

    Women Making It Work (WMIW), a grassroots network supporting women in business across Casey and Cardinia, marked its 20th anniversary with the launch of a new book sharing the personal…

  • Looking Back

    Looking Back

    100 years ago 25 February 1926 Out of his class At the Dandenong Court, Samuel Carrick was charged with travelling on the railways between Dandenong and Tooradin in the first-class…